  1. Pre-assembly Preparation:
    • Verify that all components and materials meet the specifications and model numbers as required by the design.
    • Inspect all parts for damage or defects to ensure that only good-quality parts are used.
    • Prepare the necessary tools and equipment, including lifting equipment, testing instruments, etc.
  2. Assembly Process:
    • Assemble according to the manufacturer’s instruction manual to ensure all connections are made correctly.
    • For insulating parts, ensure they are intact and installed in the correct positions.
    • During assembly, take care to prevent dust and foreign objects from entering the interior of the ring main unit.
  3. Electrical Connections:
    • Ensure all electrical connections are safe and reliable, using appropriate terminal connectors and fasteners.
    • Follow electrical safety standards when making connections to ensure their correctness and reliability.
  4. Grounding and Protective Measures:
    • Ensure all metal parts of the ring main unit are properly grounded.
    • Check all protective measures, such as insulating shields and door locks, to ensure they function correctly.
  5. Testing:
    • After assembly is complete, conduct necessary electrical tests, such as insulation resistance tests, loop resistance tests, and grounding resistance tests.
    • For key components like vacuum circuit breakers, perform vacuum degree tests and mechanical operation tests.
    • Conduct overall withstand voltage tests to ensure the ring main unit can withstand the specified working voltage and overvoltage.
  6. Functional Testing:
    • Test all operational functions of the ring main unit, including manual and automatic operations, to ensure they work properly.
    • Check the responsiveness and accuracy of the protective devices and control systems.
  7. Safety Inspection:
    • Ensure all safety measures are in place during the testing process to prevent accidents.
    • After testing is complete, conduct a thorough safety inspection to ensure no safety hazards have been overlooked.
  8. Documentation and Reporting:
    • Record all test data and results for subsequent analysis and reference.
    • Prepare a test report detailing the testing process and outcomes, as well as any issues identified and measures taken.

By following these technical points, the assembly and testing of ring main units can be carried out smoothly, ensuring the equipment operates safely and reliably once put into service.